Installing a UPS for priority consumers of the house
Feb 25, 2022
This project was implemented in three stages. At the first stage, we conducted an inspection of the existing power supply system. At the second stage, we selected the right type of UPS with external batteries, taking into account the customer’s wishes. At the third stage, we implemented the project. Please see a step-by-step implementation of the project below.
The results of the inspection of the power supply system of the BC building
The existing power supply system of the house (Photo 1):
Photo 1. The existing power supply system of the house
Solution
The customer focused on the installation of a diesel power plant that would power the entire house during the loss of mains voltage. Let’s see the advantages and disadvantages of a diesel power plant (DPP).
DPP advantages:
DPP disadvantages:
Let’s see the advantages and disadvantages of an on-line uninterruptible power supply (UPS).
UPS advantages:
UPS disadvantages:
Based on the above, we came to the conclusion that it was necessary to install a DDP and a UPS to ensure maximum reliability of the house power supply. But considering the cost of DPP with a UPS and taking into account all the advantages and disadvantages, this solution was rejected.
Having identified the customer’s needs and capacities, we proposed the optimal solution – install an on-line UPS with external rechargeable batteries with run life between 30 minutes and 2 hours, without DPP. We allocated priority consumers of the house to be supplied by UPS in order to optimize this solution as much as possible:
Project implementation